Momscode - Al Manarah - PMS Manpower Schedule
Project
PMS Manpower Schedule
The PMS Manpower Schedule is a strategic planning tool used to Forecast and Allocate Human Resources for a specific Project
Prerequisites,
- Project
Go to PMS Manpower Schedule List and Click on "Add PMS Manpower Schedule"

- Select Project
- The Project Name, Start Date, Finish Date and Total Duration will be auto fetched
- In PMS Activity Details Table, Enter Data in all fields (Activity Id, Activity Name, Original Duration, Start Date, Finish Date, Manpower)
- Alternatively, use the 'Upload' button to Import your Activity data directly from an external file
- Save
- Click on "Create Activity Plan Record"
- Activity Plan Record will be auto generated

Activity Plan Record
This document is used to record date-wise Manpower Allocation for each Activity. The Manpower percentage is updated accordingly
- The Details will be auto fetched from PMS Manpower Schedule
- In Daily Activity Progress Table, Select Date and Cumulative Manpower, the Cumulative Manpower % will be auto calculated
- Alternatively, use the 'Upload' button to Import your Daily Activity Progress data directly from an external file
- Save and Submit
- Go back to PMS Manpower Schedule and Submit

Note:
If the PMS Manpower Schedule requires modifications, a new Schedule must be created with the updated data. Saving the new version will automatically Deactivate the previous schedule and set the new one as the Active baseline